The design checks we perform
Prestress losses and transfer stresses
We calculate initial and long-term losses (PCI simplified method) and check top and bottom fibre stresses at release, including the concrete strength required for transfer and first lift.
Service stresses and composite action
We check the unshored unit under its own weight and the wet topping, then the composite section under superimposed dead and live load, against the ACI 318-19 stress limits.
Ultimate flexural capacity
We confirm the design moment strength along the full span, including strand development near the ends. For the 15.5 m unit, the factored moment of 1,267 kN·m is resisted by a design strength of 1,755 kN·m.
Vertical and horizontal shear
We design the stem shear reinforcement for the critical sections near the supports, and check horizontal (interface) shear between the precast flange and the topping.
Camber, deflection and vibration
We track camber and deflection at transfer, erection, completion and final service using PCI multipliers, and check the floor's fundamental frequency against walking-vibration limits (5.8 Hz against a 3.0 Hz minimum).
Dapped-end connections and bearing
We design the dapped ends to the PCI Design Handbook: the depth of the cut, the shear span-to-depth ratio, direct shear, hanger and flexural-tension reinforcement, with a horizontal restraint force of 20% of the vertical reaction. We also confirm the bearing length (150 mm provided against 86 mm required for span/180).
Demoulding, lifting and handling
We size the lifting anchors with factors for mould adhesion, crane dynamics and sling angle, and check the anchor-bar development length and stresses in the unit at each lifting stage.
Installed Double Tee Floor
Analysis Model of the Double Tee Unit
Flexure Check at Final Service (ACI 318-19)
Camber and Deflection at Final Service
Reinforcement, Dapped End and Lifting Details
Governing standards and how we apply them
ACI 318-19
Primary code for load combinations, prestressed flexure and shear strength, serviceability stress limits, bearing length, and anchorage of lifting inserts.
PCI Design Handbook (MNL-120, 7th edition)
Applied for prestress losses, camber and deflection multipliers, dapped-end design and handling of double tee units.
ASTM A416 and BS 4449
Grade 270 (1860 MPa) low-relaxation seven-wire strand and Grade 500B reinforcement, with C48/60 precast concrete and a C32/40 topping.
Why choose Precasterz for double tee design
Factory-to-floor verification
We check every stage the unit goes through, because transfer, demoulding and lifting often govern a long, slender double tee before the final load does.
Connection detailing that can be built
Our dapped-end and bearing details are drawn with real covers, clearances and bar bends, so the reinforcement fits in the stem and the unit seats correctly on site.
Complete calculation package
You receive a structured design memo with criteria, loading plans, analysis output, connection and lifting checks, and the final reinforcement details, ready for consultant approval.